Project's results

240

Volunteers

19699

Volunteering days

24

Nacionalities

Project Indicators

Project Deliverables and Milestones

Actions A – implementation actions

A.1 – Co-Definition of Joint Volunteering Program and Preparation of Individual Volunteering Plans

Expected – 98%
Achieved so far – 100%

Expected – 5
Achieved so far – 3

Expected – 10
Achieved so far – 18

A.2 – Updating information on concrete Conservation Areas and Detailing Conservation Activitivies/Tasks

Expected – 7
Achieved so far – 53

Expected – 3
Achieved so far – 4

A.3 – Joint Volunteering Program for integration of ESC with Nature and Biodiversity Conservation

A.4 – Volunteering for awareness-raising on natural capital protection, conservation and enhancement

A.5 – Volunteering Activities for Green Infrastructure within the Municipality of Montemor-o-Novo

Expected – 12 ha
Achieved so far – 8,7 ha

Expected – 1,2 ha
Achieved so far – 2,22 ha

Expected – 8 ha
Achieved so far – 6,48 ha

Expected – 2000
Achieved so far – 2500

Expected – 80%
Achieved so far – in progress

A.6 – Volunteering Activities for improvement of nature and biodiversity conservation in private land

A.7 – Volunteering Activities for nature conservation within the Municipality of Torres Vedras

A.8 – Volunteer Programs for Native Habitats Restoration, Promotion and Conservation and Management of Visitation Impacts

A.9 – Volunteering Activities for nature conservation along the Rota Vicentina Nature Trail

A.11 – Volunteering Activities for Conservation of Riparian/Aquatic Habitats within the Regional Structure for Environmental Protection and Conservation

Actions B - Actions of communication and awareness rising

B.1 – Definition and Implementation of Communication Program

Expected – 250
Achieved so far – 4633

Expected – 5000
Achieved so far – 1427

Expected – 20
Achieved so far – 7

Expected – 4
Achieved so far – 4

Expected – 10
Achieved so far – 3

Expected – 20
Achieved so far – 7

Expected – 40
Achieved so far – 66

B.2 – Production and Deployment of Teaser(s) to Raise Awareness and Engage ESC Volunteers

Expected – 175
Achieved so far – 50

Expected – 120000
Achieved so far – 7133

Expected – 100
Achieved so far – 82

Expected – 2000
Achieved so far – 2258

Expected – 2000
Achieved so far – 473

B.3 – Production and Deployment of TV Series for Dissemination, Replication and Transfer

Expected – 500000
Achieved so far – 0

Expected – 100
Achieved so far – 0

Expected – 200
Achieved so far – 0

Actions C – Project management and monitoring of the project progress

C.1 – Overall Project, Partnership and Stakeholder Management

Expected – 3
Achieved so far – 3

Expected – 18
Achieved so far – 24

Expected – 4
Achieved so far – 2

Expected – 20
Achieved so far – 6

C.2 – Overall Management of the ESC Volunteering Cycle

Expected – 3
Achieved so far – 2

Expected – 2
Achieved so far – 1

Expected – 100%
Achieved so far – 100%

Expected – 100%
Achieved so far – in progress

C.3 – External Audit

C.5 – Drafting and delivering the After-LIFE Plan

Expected – 1
Achieved so far – in progress